Published by Peter Dexter on 28 Feb 2012
Progress Report in Bei Cala, 14 Feb 2012
Starting date 10/02/2012 and 11/02/2012
Some of the major things we finished were:
- Front Foundations completed on 14/02/12, Length 36 Meter deep foundations 50 cm based
- Goods were on hand:
- Rocks are running low and Sends were indoors
- Cement 40Kg
- Reinforcing deformed steel bar 10mm & 6mm
Some of the important things have not finish were:
- Foundation constructions is ongoing, starting date 06/02/2012 Estimations unknown if not rain possibly will completed in 6 days.
A challenge I overcome was:
None
Problem I have:
- It seem like not sufficient rocks for foundations and Reinforcing deformed steel bar, I had asked vendor to collect 25 trucks to be pay in next budget.
- Whether raining seasons can be affect for delaying,we are not able to finish within six days.
My Target for next week are:
- Work Foundation (order conrict brict qty 2500 to be pay on next budget)
- Back fill
Jino Pereira
14/02/12