Update on Bei Cala Pre-School
Below is the latest letter from JIno and manager in Timor Leste.
Boa tarde Deb,
See the attached photos for Pre-School Project, the project has reached 80%. I am looking to finish off the last 20% in 2 months’ time.
Materials that we need in short future,
-
Windows sheets & Doors Sheets
-
Plywood for ceiling
-
We running out of sands (require for flooring ,Wall Plaster, Toilet, & Steps)
-
Paint (Please advise what color of paint would you like to suggest for the wall?)
-
Paint (Please advise what color of paint would you like to suggest for the ceiling?)
-
Roofing nails (More 15KG)
-
Ceiling roofing (10KG)
-
Wickes Treated Roofing Batten
-
Size 25X38X48MM Qty 25
-
Size 25x50x36MM Qty 30
-
Size 25x38x36MM Qty 30
Also for your info, Pre-School is close to Primary School with the distance between being only 60 meters. There was a cement green tank right in front of Pre-school building, I think in the future we can run a pipe from main tank direct to Pre-School’s toilet at the back.
Pre-School building is not far from Dad & Mum’s house we could walk in six minutes time. Pre-School building is also surrounded by community garden as you could see on the photos.
Community usually called me twice a week ask me to finish it soon therefore they could send their kids to study at pre-school.
All the boys are having a weeks off from today until we get all the materials than they start work again.
Thanks,
Adeus,
Jino Pereira